Balfour Beatty VINCI has completed the first section of the bridge that will carry the A45 over the HS2 route, with work on the second half due to start in the new year and the structure expected to be complete by the end of 2027.

HS2 has reached the halfway point in the construction of the new Coventry Road overbridge, which will allow the high-speed railway to pass beneath the A45 between Stonebridge Island and Junction 6 of the M42.
Over the past 11 months, engineers working for HS2’s construction partner Balfour Beatty VINCI (BBV) have completed the first section of the structure, near Bickenhill. The bridge is being built in two halves so that existing traffic flows along the A45 can be maintained, limiting the impact on the local road network. HS2 describes the structure as unique, given the need to build it in two halves while keeping the A45 open to traffic. Once complete, it will carry the road over four railway tracks.
How the first half of the bridge was built
BBV used a top-down construction method, with approximately 7,500 tonnes of earth excavated from beneath the existing carriageway. The team then installed 46 piles, at depths of up to 23 metres, and built pile caps to support the weight of the new 2,000-tonne bridge deck.
During the summer, 13 pre-stressed pre-cast concrete beams were lowered into place to support the 37-metre span deck, and 13 parapet units were installed on one half of the structure. Waterproofing and highway works are due to be completed in the coming weeks, after which the eastbound section will be brought into use.
Construction of the bridge in two halves is a complex engineering challenge, and reaching the halfway stage is an important milestone for the project.”
Traffic switchover from December
HS2 is working with National Highways to prepare for the traffic management changes. From Monday 7 December, a series of overnight and weekend closures will be put in place to facilitate the switchover. Once this is complete, motorists will begin using a temporary carriageway alignment over the new eastbound section of the bridge, allowing work to move on to the second half of the structure.
Paul Marshall, Head of Delivery at HS2 Ltd, said: “Our engineers have worked incredibly hard to develop a design solution that maintains traffic flows in each direction, while we build the bridge and excavate the ground below to make way for the new high-speed railway.
“During the temporary weekend and night-time closures, to facilitate the traffic switchover onto the new bridge, we’ll ensure that access to businesses and properties is maintained.
“I’d encourage motorists to familiarise themselves with the diversion routes and thank them for their patience.”
Second section and the route to Interchange Station
In the new year, BBV’s engineering team will start work on the second section of the bridge, following a similar sequence of works. Below the structure, hidden from view, the team will continue excavating the trace, which will ultimately carry four railway tracks towards the new Interchange Station, about one mile away. The tracks will serve the station’s four platforms, which are made up of two 425-metre-long platform islands.
Richard Husbands, Balfour Beatty VINCI’s Project Manager, said: “The Coventry Road overbridge is one of the key crossings on this part of the route, allowing the railway to pass under the A45 as it approaches Interchange Station. Construction of the bridge in two halves is a complex engineering challenge, and reaching the halfway stage is an important milestone for the project.
“The programme we’re working to has been designed to minimise disruption for motorists and local communities as much as possible. We’re grateful for everyone’s continued patience, as we move to the next phase of construction.”
Above ground, construction will continue throughout 2027, and the bridge is expected to be structurally complete by the end of that year. Working with National Highways, engineers will then carry out the permanent highway works, installing lighting, kerbs, drainage and a permanent carriageway. The final structure and road alignment are expected to be in use by summer 2028, following the temporary traffic arrangements that begin in December.