Latest phase of London Bridge Thameslink Programme successfully delivered
Posted: 2 September 2015 | | No comments yet
Network Rail reveals the latest phase of Thameslink Programme rebuilding work at London Bridge was successfully delivered during the bank holiday period. The work carried out as part of the Government-sponsored Thameslink Programme saw the installation of more than 1km of new track, a massive new signal gantry near Waterloo East, several new sets of […]


Network Rail reveals the latest phase of Thameslink Programme rebuilding work at London Bridge was successfully delivered during the bank holiday period.
The work carried out as part of the Government-sponsored Thameslink Programme saw the installation of more than 1km of new track, a massive new signal gantry near Waterloo East, several new sets of points fitted and more than 6km of power cables laid. Work for the Thameslink Programme in and around London Bridge is currently being carried out in stages until 2018.
As a result of the work, there were no trains to or from Charing Cross, Waterloo East, Cannon Street and parts of London Bridge over all three days of the holiday.
Thameslink Programme rail systems director Mark Somers said: “I’d like to thank passengers and our neighbours for their patience this Bank Holiday as we have completed more work around London Bridge.
“Every weekend where we can do work on this scale is absolutely massive for us. Every single piece of track and every piece of equipment we put in position this weekend is crucial for Christmas, which will be the vital next stage for the project.”
Additional work included the installation of two new sets of crossovers at Ewer Street, near Waterloo East, in preparation for when Charing Cross trains start using the new Borough Market Viaduct. A redundant signal gantry was removed from the eastern approaches to London Bridge and two tracks used by Charing Cross trains immediately outside London Bridge station were ‘slewed’ or cut and moved to the north. This will allow for the old track and right-of-way to be dug up and rebuilt in time for Christmas and the next major stage of rebuilding.
Stay Connected with Global Railway Review — Subscribe for Free!
Get exclusive access to the latest rail industry insights from Global Railway Review — all tailored to your interests.
✅ Expert-Led Webinars – Gain insights from global industry leaders
✅ Weekly News & Reports – Rail project updates, thought leadership, and exclusive interviews
✅ Partner Innovations – Discover cutting-edge rail technologies
✅ Print/Digital Magazine – Enjoy two in-depth issues per year, packed with expert content
Choose the updates that matter most to you. Sign up now to stay informed, inspired, and connected — all for free!
Thank you for being part of our community. Let’s keep shaping the future of rail together!