Network Rail completes Easter work programme despite storm conditions
Posted: 29 March 2016 | | No comments yet
Network Rail has completed its Easter improvement works despite a large section of the UK experiencing poor weather conditions with the arrival of Storm Katie.


Network Rail has completed its Easter improvement works despite a large section of the UK experiencing poor weather conditions with the arrival of Storm Katie.
A record 450 engineering projects were completed over the Easter break in spite of Storm Katie causing damage across large swathes of southern Britain.
“Dealing with the damage caused by Storm Katie would have been challenging in itself, but it came on top of the biggest programme of Easter engineering works ever”
Network Rail chief executive, Mark Carne, said: “Dealing with the damage caused by Storm Katie would have been challenging in itself, but it came on top of the biggest programme of Easter engineering works ever. I am immensely proud of the dedicated people who worked so hard to safely deliver over 450 improvement projects that will make a difference to passengers and businesses who rely on the railway every day.”
As Storm Katie battered Britain on Monday 28 March, overhead electrical wires were damaged on the East Coast mainline, a wall collapsed onto the tracks in north-west London, part of the roof was blown off a station in Bognor and over 100 trees were blown onto the railway in the south east of England. Engineers were drafted in overnight to clear lines, make repairs and keep passengers and freight moving.
£60m Network Rail Easter investment programme…
Network Rail’s £60m Easter investment programme, part of the £40bn Railway Upgrade Plan, saw the building and construction of new station facilities, longer platforms, extra tracks, new junctions and the installation of new equipment.
In and around London, overhead lines were renewed and Crossrail work was completed on the Great Eastern Main Line, while old track was replaced near Waterloo.
In Manchester, a major nine-day programme of work was started to improve the track layout at Manchester Victoria station as part of Network Rail’s Northern Hub project.
In Scotland, work continued to replace 1,800m of ageing track leading up to Glasgow Queen Street station to allow faster, greener and longer trains to run between Glasgow and Edinburgh.
Between Reading and London, work was completed to make way for electric trains and Crossrail, and in Kent signals were upgraded to improve the reliability of the railway for passengers.
NEW REPORT FROM GLOBAL RAILWAY REVIEW: Track Insight – Track Maintenance | Transforming Track Maintenance Through Technology
Our latest expert-led Track Insight explores how industry leaders are revolutionising the future of track maintenance through cutting-edge innovation and real-world strategies.
From automation and robotics now streamlining inspections and repairs, to predictive maintenance powered by IoT sensors and advanced analytics, the rail sector is entering a new era of precision and efficiency. Companies like Goldschmidt, Bentley Systems, and MxV Rail are leading the charge, redefining how infrastructure is managed with AI, machine learning, and digital twins to reduce downtime and extend asset life.
In this new data-rich landscape, organisations such as Amtrak and the Rail Accident Investigation Branch are demonstrating how to turn vast streams of information—from track geometry to environmental monitoring into actionable intelligence for safer, smarter networks.
Download this insightful, practical guide for FREE and see how your operations can evolve – READ FOR FREE NOW!
Related topics
Adverse Weather, Track/Infrastructure Maintenance & Engineering