The Tram Train pilot is set to achieve a key milestone
Posted: 31 March 2017 | | No comments yet
The Tram Train project in South Yorkshire will soon take a significant step towards completion as construction work continues.


The Tram Train project in South Yorkshire will soon take a significant step towards completion as construction work continues.
This significant step is the replacement of College Road bridge in Rotherham to make way for a new, higher bridge to be installed so the overhead lines (which power the Tram Trains) can be safely installed underneath.
The old bridge will be demolished using a crane and work will also be carried out to bring the signalling system, which controls Tram Train movements, into operation.
“Tram Trains will bring new travel choices for people living in South Yorkshire as well as being a first for the UK”
“Tram Trains will bring new travel choices for people living in South Yorkshire as well as being a first for the UK,” said Rob Cairns, Route Delivery Director for Network Rail. “The work we have planned is a crucial step forward as we work with our partners to deliver the full Tram Train service from Sheffield city centre to Rotherham Central and Parkgate next year.”
The Tram Train pilot will help the rail industry understand and assess the technical issues involved with planning and operating a Tram Train service. It will be the first time a Tram Train system has operated in the UK and is delivered by South Yorkshire Passenger Transport Executive (SYPTE), Network Rail, Northern, Stagecoach Supertram and the Department for Transport (DfT).
“The pilot has the ability to transform transport connections both locally and nationally”
“Passengers in South Yorkshire will be the first in the country to benefit from pioneering Tram Trains,” added Stephen Edwards, Executive Director for SYTPE. “The pilot has the ability to transform transport connections both locally and nationally, and the College Road bridge engineering work is an important milestone towards making Tram Trains a reality from 2018.”
To allow for these works, College Road will be closed for 18 weeks from Friday 14 April to Friday 18 August 2017. To find out more information about the Tram Train project go to sypte.co.uk/tramtrain
OUT NOW: The Definitive Guide to Rail’s Digital Future
The rail industry is undergoing a digital revolution, and you need to be ready. We have released our latest market report, “Track Insight: Digitalisation.”
This is not just another report; it’s your comprehensive guide to understanding and leveraging the profound technological shifts reshaping our industry. We move beyond the buzzwords to show you the tangible realities of AI, IoT, and advanced data analytics in rail.
Discover how to:
- Optimise operations and maintenance with real-time insights.
- Enhance passenger services through seamless, high-speed connectivity.
- Leverage technologies like LEO satellites to improve safety and efficiency.
Featuring expert analysis from leaders at Nomad Digital, Lucchini RS, Bentley Systems and more, this is a must-read for any rail professional.