Tunnel progress as HS2 achieves first mile under the Chiltern hills

0
SHARES

Posted: 1 October 2021 | | No comments yet

The 2,000 tonne Tunnel Boring Machine, Florence, has surpassed the one-mile mark during construction of the first tunnels for Britain’s new high-speed rail link between London, Birmingham and the north.

Tunnel progress as HS2 achieves first mile under the Chilterns hills

Credit: HS2 Ltd

Launched in May 2021, the 170m long Tunnel Boring Machine (TBM) covered the first mile cutting through a mix of chalk and flint beneath the Chiltern hills just outside London.

Named ‘Florence’ by local school children, the TBM is one of two identical machines excavating the twin 10-mile-long tunnels. A second machine, named ‘Cecilia’ is a short way behind, with both TBMs expected to break out in around three years’ time.

Designed specifically for the geology of the Chilterns, each machine is a self-contained underground factory, digging the tunnel, lining it with concrete wall segments and grouting them into place as it moves forward.

Welcoming the progress, HS2 Ltd Project Client, Rohan Perin said: “The 10 mile Chiltern tunnel will  take HS2 underneath the hills and safeguard the woodlands and wildlife habits above ground, as well as significantly reducing disruption to communities during construction and operation of the new railway.

“Once complete, HS2 will offer low carbon journey options linking London with the major cities of the north and releasing capacity for more freight and local trains on our existing mainlines. It’s great to see how much progress has been made over the summer and I’d like to thank the crew of Florence and all the tunnelling team for their hard work.”

The first two TBMs are operated by HS2’s main works contractor, Align – a joint venture formed of Bouygues Travaux Publics, Sir Robert McAlpine, and VolkerFitzpatrick.

A crew of 17 people keep the machines running, working in shifts and supported by over 100 people on the surface, managing the logistics and maintaining the smooth progress of the tunnelling operation.

Daniel Altier, Align Project Director added: “I am delighted with the progress that Florence has made since its launch in May, with Cecilia not far behind. All the spoil from the TBMs is converted into slurry before being pumped back to our South Portal site, just inside the M25, where it is processed and used for landscaping on site. This is, and will continue to be, a huge logistical challenge, as Florence and Cecilia continue their journey through the Chilterns.

“Florence reaching the one-mile point is a great achievement, however we still have a long way to go.”

Each of the separate northbound and southbound tunnels will require 56,000 precision engineered, fibre-reinforced concrete wall segments – which are all being made at the south portal of the tunnel, next to the M25. During her first mile, Florence and her crew have installed more than 5,500 separate segments, each weighing around 8.5 tonnes.

Approximately 2.7 million cubic metres of material will be excavated during the construction of the tunnels and used for landscaping around the south portal site. Once construction is complete, this will help create around 90 hectares of wildlife-rich chalk grassland habitats. Chalk grassland used to be widespread across the hills of south east England and are considered habitat of international conservation significance with just 700ha left across the Chilterns.

In total there will be 10 TBMs on the HS2 project – working to create 64 miles of tunnel between London and the West Midlands including major tunnels on the approach to London and Birmingham.

More than 20,000 jobs and over 650 apprenticeships are already being supported by HS2, which is set to transform transport links between Britain’s major cities, free up space on the rail network for more freight and local services and support the UK’s transition to net-zero carbon emissions.

OUT NOW: The Definitive Guide to Rail’s Digital Future

The rail industry is undergoing a digital revolution, and you need to be ready. We have released our latest market report, “Track Insight: Digitalisation.”

This is not just another report; it’s your comprehensive guide to understanding and leveraging the profound technological shifts reshaping our industry. We move beyond the buzzwords to show you the tangible realities of AI, IoT, and advanced data analytics in rail.

Discover how to:

  • Optimise operations and maintenance with real-time insights.
  • Enhance passenger services through seamless, high-speed connectivity.
  • Leverage technologies like LEO satellites to improve safety and efficiency.

Featuring expert analysis from leaders at Nomad Digital, Lucchini RS, Bentley Systems and more, this is a must-read for any rail professional.

Access your copy now!

 

 

 

 

 

Share via
Share via